Beaconsfield Timber and Hardware P/L are proud to announce the joining of forces with HoME Hardware. Beaconsfield HoME Timber and Hardware P/L will be part of a group of some 240 independantly owned stores Australia wide. Located on our existing site with the new address of 102-112 Old Princes Highway entry and parking will be a breeze. Remaining family owned and run and with all your familiar faces we will provide the complete Hardware offer to compliment our existing trade and timber business. Our new purpose built store of some 2500 square metres will include a nursery, outdoor furniture, paint, homewares, powertools, plumbing and electrical supplies to cater for the growing needs of the local area.


In planning for close to three years, drainage and earthworks commenced 19th June 2007. Including a massive drainage retention system clearing and leveling the site has taken two months. The building, designed and constructed by Safety Steel Structures in Dandenong is being built in two stages. Footings for stage one were dug and poured on 30th August, using some 50 m3 of concrete.

Please click on the image to see a larger version...


Steel work was delivered on the 10th of September and the columns were erected the following day. The 12th of September saw the assembling of roof trusses which were then stood up and bolted into place at ground level. The roof is to be built on the ground and then lifted into place via block and tackles pre installed on top of the columns, with the use of electric motors, once all insulation and roof sheets have been installed, at ground level. Quite an amazing system which makes the building process much simpler and much safer for the workers on site. The roof was winched into place on the 26th September.Quite an amazing sight which took all of 20 minutes to happen.




Concrete wall panels arrived and were craned into place on Monday 1st of October. The footings have also been dug and poured ready for the next stage to commence.



Early November saw the steel work up, roof built and lifted into place and concrete panels into position within days. With the shell now complete the building is really taking shape now although there is still lots of services to run inside before the concretre floor will be poured early December and have the building locked up by Christmas.



Car parks and driveway concrete will commence early January along with shade sails and two huge underground water tanks for the nursery. New offices and counters will also follow and then the massive job of installing shelving and racking for stock to arrive and be set up.

We are hoping to be finished construction and all things going well up and trading by March or April 2008.